Wilmington-Delaware State Auditor, a warden of the port of Wilmington, Lydia York, has announced that her office will open an investigation into the State Port Corporation Diamond (DSPC), the state entity that runs the port facility and directs $ 635 million.

The audit, called the performance audit, will look at Port Corporation’s Port Corporation operations more in depth from the standard audit financial audit.

“The implementation audit will look at more of their processes and how they receive funds, they need to spend funds and how they are regulated,” Lydia York said.

In 1995, Delaware bought the port from Wilmington and created the Diamond State Port Corporation to operate the facility. The port of Wilmington is located in the merger of the Delaware and Christina rivers and is the most loaded terminal of the Delaware River.

The port generates millions of dollars revenue for the state every year. The port is a key economic engine for Delaware and is expected to become even more important in the construction of a new terminal.

“This is a significant industrial development- in the neighborhood with or inside the city of Wilmington.”

The audit will lead to a report that contains the auditor’s opinion and the confidence that the port is working effectively, looking at how the port corporation has processed hundreds of millions of dollars in taxpayer fund For the fiscal 2025.

“There may be interviews, there may be inquiries,” York said. “We will just ask-for questions-,-searching for documentation about the cause and answers that started.”

The audit will investigate how the port corporation has spent money on the Edgemoor expansion project. The Edgemoor project is planned to expand Wilmington port to build a new port terminal on a site in Edgemoor, Delaware. The Edgemoor industrial site was purchased by DSPC in 2017.

The project was delayed due to financial issues, opposing neighbors and conflicts with permits.

“Construction has been suspended because they have no permits,” York said.

Asked if the plans are on a break so far, York replied: “Just because you don’t dig, it doesn’t mean you don’t plan and I would expect it is happening now.”

According to the auditor of the Account Office, the state funds for a total of nearly $ 200 million have recently been transferred from the exclusive Escheat claims at the State Corporation Diamond State for the Edgemoor extension project.

The funds were intended by the former Secretary of Finance, the former director of the Budget of the Management Office and the Chairperson of the Joint Committee on Capital Improvement. The process is described in detail in the language of the epilogue of the bonds on fiscal year 2023 and the fiscal 2024. The money is kept in a state special fund bearing interest from June 2024.

The transfer followed the signing of a joint development agreement between the Diamond State Port Corporation and Enstructure in December.

“I think with every major project, especially the one who finances this dollar capacity (the Wilmington Community) will want to be protected and that the benefit will come to the city of Wilmington,” she said.

To the extent that the audit will take, York explained that they were still in the most stages. We are now focusing on providing all the necessary internal resources when the work is to be done. The audit process must be planned where the scope is established and the work must still be outlined. Individual procedures are performed to validate the scope, which leads to conclusions as part of the overall process.

“We think it will be fast, but it may feel slow, but the time we spend will be well spent, and I think everyone will find the results informative.”